Summary
1. A national court may, under the Protocol of 3 June 1971 on the interpretation by the Court of Justice of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters, as amended by the Convention of 9 October 1978 on the Accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland, by the Convention of 25 October 1982 on the Accession of the Hellenic Republic, by the Convention of 26 May 1989 on the Accession of the Kingdom of Spain and the Portuguese Republic and by the Convention of 29 November 1996 on the Accession of the Republic of Austria, the Republic of Finland and the Kingdom of Sweden, refer to the Court of Justice a request for interpretation of the Brussels Convention, even where it relies on the submissions of a party to the main proceedings of which it has not yet examined the merits, provided that it considers, having regard to the particular circumstances of the case, that a preliminary ruling is necessary to enable it to give judgment and that the questions on which it seeks a ruling from the Court are relevant. It is nevertheless incumbent on the national court to provide the Court of Justice with factual and legal information enabling it to give a useful interpretation of the Convention and to explain why it considers that a reply to its questions is necessary to enable it to give judgment.
see para. 27, operative part 1
2. Article 21 of the Brussels Convention must be interpreted as meaning that a court second seised whose jurisdiction has been claimed under an agreement conferring jurisdiction must nevertheless stay proceedings until the court first seised has declared that it has no jurisdiction.
That fact is not such as to call in question the application of the procedural rule contained in Article 21 of the Convention, which is based clearly and solely on the chronological order in which the courts involved are seised.
see paras 47, 54, operative part 2
3. Article 21 of the Brussels Convention of 27 September 1968 must be interpreted as meaning that it cannot be derogated from where, in general, the duration of proceedings before the courts of the Contracting State in which the court first seised is established is excessively long.
An interpretation whereby the application of that article should be set aside in such a situation would be manifestly contrary both to the letter and spirit and to the aim of the Convention.
see paras 70, 73, operative part 3
Publication reference
-
Publication reference: European Court Reports 2003 I-14693
Document number
-
ECLI identifier: ECLI:EU:C:2003:657
-
Celex-Nr.: 62002CJ0116
Authentic language
-
Authentic language: German
Dates
-
Date of document: 09/12/2003
-
Date lodged: 02/04/2002
Classifications
Miscellaneous information
-
Author: Court of Justice
-
Country or organisation from which the decision originates: Austria
-
Form: Judgment
Procedure
-
Type of procedure: Reference for a preliminary ruling
-
Judge-Rapportuer: Schintgen
-
Observations: EUMS, United Kingdom, Italy, European Commission, EUINST
-
National court:
- *A9* Oberlandesgericht Innsbruck, Beschluß vom 25/03/2002
- - International Litigation Procedure 2002 p.212-232
- *P1* Oberlandesgericht Innsbruck, Beschluß vom 09/01/2004
Legal doctrine
Mance, Jonathan: Exclusive Jurisdiction Agreements and European Ideals, The Law Quarterly Review 2004 p.357-365 (EN)
Véron, Pierre: ECJ Restores Torpedo Power, International Review of Industrial Property and Copyright Law 2004 p.638-642 (EN)
Taschner, Martin: Ausnahmen von der Rechtshängigkeitssperre nach Art. 27 Abs. 1 EuGVO?, Europäisches Wirtschafts- & Steuerrecht - EWS 2004 p.494-500 (DE)
Vlas, P.: Nederlandse jurisprudentie ; Uitspraken in burgerlijke en strafzaken 2007 nº 151 (NL)
Nurmela, Ilona ; Põldvere, Pirkka-Marja: Vaidluste efektiivne kohtuväline lahendamine, Juridica: Tartu Ülikooli õigusteaduskonna ajakiri 2014 nº 1 p.3-16 (ET)
Fentiman, Richard: Common Market Law Review 2005 p.241-259 (EN)
Idot, Laurence: Litispendance. L'article 21 sur la litispendance doit s'appliquer même lorsque le juge saisi en second est compétent sur la base d'une clause attributive de juridiction, Europe 2004 Février Comm. nº 58 p.22 (FR)
Bruneau, Chantal: Litispendance européenne et clause attributive de juridiction, Recueil Le Dalloz 2004 Jur. p.1046-1050 (FR)
Wittwer, Alexander: Auch bei italienischer Prozessdauer gilt Art. 21 EuGVÜ, European Law Reporter 2004 p.49-50 (DE)
Meidanis, Ch.: Diki 2006 p.825-831 (EL)
Romano, Gian Paolo: Le principe de sécurité juridique à l'épreuve des arrêts Gasser et Owusu, Cahiers de droit européen 2008 p.175-210 (FR)
Bonassies, Pierre ; Delebecque, Philippe: Le droit maritime français 2005 p.94-95 (FR)
Clavel, Sandrine: Droit de l'arbitrage, Petites affiches. La Loi / Le Quotidien juridique 2009 nº 53 p.16-17 (FR)
Saf, Carolina: Internationell litispendens, Juridisk Tidskrift vid Stockholms universitet 2004 p.653-662 (SV)
Mankowski, Peter: Entscheidungen zum Wirtschaftsrecht 2004 p.439-440 (DE)
Otte, Karsten: Zeitschrift für Zivilprozeß International 2003 Bd.8 p.521-527 (DE)
Schilling, Theodor: Internationale Rechtshängigkeit vs. Entscheidung binnen angemessener Frist - Zum Zusammenspiel von Art. 6 I EMRK, Art. 307 EGV und Art. 27 EuGVV, Praxis des internationalen Privat- und Verfahrensrechts 2004 p.294-298 (DE)
Muir Watt, Horatia: Revue critique de droit international privé 2004 p.459-464 (FR)
Fiumara, Oscar: La competenza del giudice preventivamente adito nella Convenzione di Bruxelles: irrilevanza di una durata eccessivamente lunga del processo, Rassegna dell'avvocatura dello Stato 2003 IV Sez.II p.64-66 (IT)
McGuire, Mary-Rose: Forum Shopping und Verweisung - Über die Vermeidung missbräuchlicher Prozesstaktiken im Europäischen Zivilprozessrecht, Zeitschrift für Rechtsvergleichung, internationales Privatrecht und Europarecht 2005 p.83-93 (DE)
Holtskog Olebakken, Ingeborg B.: Internasjonal sivilprosess - to dommer om verneting etter Brusselkonvensjonen og betydningen for norsk rett, Lov og rett 2006 nr 8-9 p.561-569 (NO)
Andrews, Neil: Abuse of process and obstructive tactics under the Brussels jurisdictional system: Unresolved problems for the European authorities Erich Gasser GmbH v MISAT Srl Case C-116/02 (9 December 2003) and Turner v Grovit Case C-159/02 (27 April 2004), Zeitschrift für Gemeinschaftsprivatrecht 2005 p.8-15 (EN)
Huet, André: Chronique de jurisprudence du Tribunal et de la Cour de justice des Communautés européennes, Journal du droit international 2004 p.641-645 (FR)
Fentiman, Richard: Access to Justice and Parallel Proceedings in Europe, The Cambridge Law Journal 2004 p.312-314 (EN)
Grothe, Helmut: Zwei Einschränkungen des Prioritätsprinzips im europäischen Zuständigkeitsrecht: ausschließliche Gerichtsstände und Prozeßverschleppung, Praxis des internationalen Privat- und Verfahrensrechts 2004 p.205-212 (DE)
Thiele, Christian: Anderweitige Rechtshängigkeit im Europäischen Zivilprozessrecht - Rechtssicherheit vor Einzelfallgerechtigkeit, Recht der internationalen Wirtschaft 2004 p.285-289 (DE)
Baatz, Yvonne: Who Decides on Jurisdiction Clauses?, Lloyd's Maritime and Commercial Law Quarterly 2004 p.25-29 (EN)
Relationship between documents
- Treaty: Treaty establishing the European Economic Community (1957)
-
Case affecting:
Affects Legal instrument Provision Interprets 41968A0927(01) A21 Interprets 41971A0603(02) -
Instruments cited:
Legal instrument Provision Paragraph in document 41968A0927(01) A28 N 10 41968A0927(01) A18 N 7 49 41968A0927(01) A02 N 4 41968A0927(01) A27 N 9 41 41968A0927(01) A16 N 5 44 41968A0927(01) A05 N 4 41968A0927(01) A22 N 41 41968A0927(01) A21 N 1 8 26 41 - 54 70 - 73 41968A0927(01) N 3 41 53 70 41968A0927(01) A17 N 6 26 46 - 54 41968A0927(01) A19 N 52 41971A0603(02) N 23 - 27 61986CJ0144 N 41 61989CJ0214 N 51 61989CJ0351 N 41 43 - 45 48 61995CJ0106 N 50 61995CJ0220 N 23 61995CJ0295 N 23 11997E234 N 23 - 27 11997E293 N 3 61997CJ0159 N 23 50 62001CJ0111 N 23 24 62002CC0116 N 26
Case C-116/02 Erich Gasser GmbHvMISAT Srl (Reference for a preliminary ruling from the Oberlandesgericht Innsbruck (Austria))
«(Brussels Convention – Article 21 – Lis pendens – Article 17 – Agreement conferring jurisdiction – Obligation to stay proceedings of court second seised designated in an agreement conferring jurisdiction – Excessive duration of proceedings before courts in the Member State of the court first seised)»
|
I - 0000 |
|
I - 0000 |
Summary of the Judgment
(Brussels Convention of 27 September 1968; Protocol of 3 June 1971)
(Brussels Convention of 27 September 1968, Art. 21)
(Brussels Convention of 27 September 1968, Art. 21)
1.
2.
3.
JUDGMENT OF THE COURT (Full Court)
9 December 2003 (1)
((Brussels Convention – Article 21 – Lis pendens – Article 17 – Agreement conferring jurisdiction – Obligation to stay proceedings of court second seised designated in an agreement conferring jurisdiction – Excessive duration of proceedings before courts in the Member State of the court first seised))In Case C-116/02, REFERENCE to the Court under the Protocol of 3 June 1971 on the interpretation by the Court of Justice of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters by the Oberlandesgericht Innsbruck (Austria) for a preliminary ruling in the proceedings pending before that court between Erich Gasser GmbH
and
MISAT Srl,on the interpretation of Article 21 of the abovementioned Convention of 27 September 1968, as amended by the Convention of 9 October 1978 on the accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland (OJ 1978 L 304, p. 1, and ─ amended text ─ p. 77), by the Convention of 25 October 1982 on the accession of the Hellenic Republic (OJ 1982 L 388, p. 1), by the Convention of 26 May 1989 on the accession of the Kingdom of Spain and the Portuguese Republic (OJ 1989 L 285, p. 1) and by the Convention of 29 November 1996 on the accession of the Republic of Austria, the Republic of Finland and the Kingdom of Sweden (OJ 1997 C 15, p. 1),THE COURT (Full Court),,
composed of: V. Skouris, President, P. Jann, C.W.A. Timmermans, C. Gulmann, J.N. Cunha Rodrigues and A. Rosas (Presidents of Chambers), D.A.O. Edward, A. La Pergola, J.-P. Puissochet, R. Schintgen (Rapporteur), F. Macken, N. Colneric and S. von Bahr, Judges, Advocate General: P. Léger, Registrar: M.-F. Contet, Principal Administrator,after considering the written observations submitted on behalf of:
─
Erich Gasser GmbH, by K. Schelling, Rechtsanwalt,─
MISAT Srl, by U.C. Walter, Rechtsanwältin,─
the Italian Government, by I.M. Braguglia, acting as Agent, assisted by O. Fiumara, Vice Avvocato Generale dello Stato,─
the United Kingdom Government, by K. Manji, acting as Agent, and by D. Lloyd Jones QC,─
the Commission of the European Communities, by A.-M. Rouchaud-Joët and S. Grünheid, acting as Agents,having regard to the Report for the Hearing,
after hearing the oral observations of Erich Gasser GmbH, the Italian Government, the United Kingdom Government and the Commission at the hearing on 13 May 2003,
after hearing the Opinion of the Advocate General at the sitting on 9 September 2003,
gives the following
Judgment
1
By judgment of 25 March 2002, received at the Court on 2 April 2002, the Oberlandesgericht (Higher Regional Court) Innsbruck referred to the Court for a preliminary ruling under the Protocol of 3 June 1971 on the interpretation by the Court of Justice of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters (the Protocol), a number of questions on the interpretation of Article 21 of the abovementioned Convention of 27 September 1968, as amended by the Convention of 9 October 1978 on the accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland (OJ 1978 L 304, p. 1, and ─ amended text ─ p. 77), by the Convention of 25 October 1982 on the accession of the Hellenic Republic (OJ 1982 L 388, p. 1), by the Convention of 26 May 1989 on the accession of the Kingdom of Spain and the Portuguese Republic (OJ 1989 L 285, p. 1) and by the Convention of 29 November 1996 on the accession of the Republic of Austria, the Republic of Finland and the Kingdom of Sweden (OJ 1997 C 15, p. 1) (the Brussels Convention or the Convention).
2
Those questions were raised in proceedings between Erich Gasser GmbH ( Gasser), a company incorporated under Austrian law, and MISAT Srl ( MISAT), a company incorporated under Italian law, following a breakdown in their business relations.
Legal background
3
4
5
Article 16 of the Convention lays down rules governing exclusive jurisdiction. In particular, pursuant to Article 16(1)(a), in proceedings which have as their object rights
in immovable property or tenancies of immovable property, the courts of the Contracting State in which the property is situated are to have exclusive jurisdiction.
6
Articles 17 and 18 of the Convention deal with the attribution of jurisdiction. Article 17 is worded as follows:If the parties, one or more of whom is domiciled in a Contracting State, have agreed that a court or the courts of a Contracting State are to have jurisdiction to settle any disputes which have arisen or which may arise in connection with a particular legal relationship, that court or those courts shall have exclusive jurisdiction. Such an agreement conferring jurisdiction shall be either:
(a)
in writing or evidenced in writing; or
(b)
in a form which accords with practices which the parties have established between themselves; or
(c)
in international trade or commerce, in a form which accords with a usage of which the parties are or ought to have been aware and which in such trade or commerce is widely known to, and regularly observed by, parties to contracts of the type involved in the particular trade or commerce concerned.
...Agreements ... conferring jurisdiction shall have no legal force if they are contrary to the provisions of Article 12 or 15 [insurance and consumer contracts], or if the courts whose jurisdiction they purport to exclude have exclusive jurisdiction by virtue of Article 16....
7
Article 18 provides: Apart from jurisdiction derived from other provisions of this Convention, a court of a Contracting State before whom a defendant enters an appearance shall have jurisdiction. This rule shall not apply where appearance was entered solely to contest the jurisdiction, or where another court has exclusive jurisdiction by virtue of Article 16.
8
: Where proceedings involving the same cause of action and between the same parties are brought in the courts of different Contracting States, any court other than the court first seised shall of its own motion stay its proceedings until such time as the jurisdiction of the court first seised is established.Where the jurisdiction of the court first seised is established, any court other than the court first seised shall decline jurisdiction in favour of that court.
9
Finally, in relation to recognition, Article 27 of the Convention provides: A judgment shall not be recognised:...
3.
if the judgment is irreconcilable with a judgment given in a dispute between the same parties in the State in which recognition is sought.
10
According to the first paragraph of Article 28 of the Convention, [m]oreover, a judgment shall not be recognised if it conflicts with the provisions ... [concerning insurance and consumer contracts and the matters referred to in Article 16].
The main proceedings and the questions referred to the Court
11
The registered office of Gasser is in Dornbirn, Austria. For several years it sold children's clothing to MISAT, of Rome, Italy.
12
On 19 April 2000 MISAT brought proceedings against Gasser before the Tribunale Civile e Penale (Civil and Criminal District Court) di Roma seeking a ruling that the contract between them had terminated
or, in the alternative, that the contract had been terminated following a disagreement between the two companies. MISAT also asked the court to find that it had not failed to perform the contract and to order Gasser to pay it damages for failure to fulfil the obligations of fairness, diligence and good faith and to reimburse certain costs.
13
14
15
16
Gasser appealed against that decision to the Oberlandesgericht Innsbruck, contending that the Landesgericht Feldkirch should be declared to have jurisdiction and that proceedings should not be stayed.
17
The national court considers, first, that this is a case of
since the parties are the same and the claims made before the Austrian and Italian courts have the same cause of action within the meaning of Article 21 of the Brussels Convention, as interpreted by the Court of Justice (see, to that effect, Case 144/86
[1987] ECR 4861).
18
19
20
It was in those circumstances that the Oberlandesgericht Innsbruck stayed proceedings and referred the following questions to the Court for a preliminary ruling:
1.
May a court which refers questions to the Court of Justice for a preliminary ruling do so purely on the basis of a party's (unrefuted) submissions, whether they have been contested or not contested (on good grounds), or is it first required to clarify those questions as regards the facts by the taking of appropriate evidence (and if so, to what extent)?
2.
May a court other than the court first seised, within the meaning of the first paragraph of Article 21 of the Brussels Convention on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters [ the Brussels Convention], review the jurisdiction of the court first seised if the second court has exclusive jurisdiction pursuant to an agreement conferring jurisdiction under Article 17 of the Brussels Convention, or must the agreed second court proceed in accordance with Article 21 of the Brussels Convention notwithstanding the agreement conferring jurisdiction?
3.
Can the fact that court proceedings in a Contracting State take an unjustifiably long time (for reasons largely unconnected with the conduct of the parties), so that material detriment may be caused to one party, have the consequence that the court other than the court first seised, within the meaning of Article 21, is not allowed to proceed in accordance with that provision?
4.
5.
6.
What course of action must the court follow if, in the circumstances described in Question 3, it is not allowed to apply Article 21 of the Brussels Convention? Should it be necessary in any event, even in the circumstances described in Question 3, to proceed in accordance with Article 21 of the Brussels Convention, there is no need to answer Questions 4, 5 and 6.
The first question
21
22
23
[2003] ECR I-4207, paragraphs 34 and 38).
24
However, the spirit of cooperation which must prevail in the preliminary-ruling procedure requires the national court, for its part, to have regard to the function entrusted to the Court of Justice, which is to assist in the administration of justice in the Member States and not to deliver advisory opinions on general or hypothetical questions. In order to enable the Court to provide a useful interpretation of Community law, it is appropriate that the national court should define the legal and factual context of the interpretation sought and it is essential for it to explain why it considers that a reply to its questions is necessary to enable it to give judgment (see to that effect
, cited above, paragraphs 35, 37 and 38).
25
According to the account of the facts given by the national court, the proposition that there may be an agreement conferring jurisdiction is not purely hypothetical.
26
Moreover, as has been emphasised both by the Commission and by the Advocate General in points 38 to 41 of his Opinion, the national court, before verifying the existence of a clause conferring jurisdiction within the meaning of Article 17 of the Brussels Convention and the existence of usage in international trade and commerce in that connection ─ a process which may necessitate delicate and costly investigations ─ considered it necessary to refer to the Court the second question, to establish whether the existence of an agreement conferring jurisdiction allows non-application of Article 21 of the Brussels Convention. If that question is answered in the affirmative, the national court will have to rule as to the existence of such an agreement conferring jurisdiction and, if the existence thereof is established, it will have to consider itself to have exclusive jurisdiction to give judgment in the main proceedings. Conversely, if the answer is in the negative, Article 21 of the Brussels Convention will have to apply, so that the question whether there is an agreement conferring jurisdiction will no longer be an issue with which the national court is concerned.
27
The second question
28
Observations submitted to the Court
29
rule.
30
31
The United Kingdom Government adds that it is necessary to examine the relationship between Articles 17 and 21 of the Brussels Convention taking account of the needs of international trade. The commercial practice of agreeing which courts are to have jurisdiction in the event of disputes should be supported and encouraged. Such clauses contribute to legal certainty in commercial relationships, since they enable the parties, in the event of a dispute, easily to determine which courts will have jurisdiction to deal with it.
32
33
Finally, the United Kingdom Government concedes that the thesis which it defends might give rise to a risk of irreconcilable judgments. To avoid that risk, it proposes that the Court hold that a court first seised whose jurisdiction is contested in reliance on an agreement conferring jurisdiction must stay proceedings until the court which is designated by that agreement, and is the court second seised, has given a decision on its own jurisdiction.
34
35
36
The Commission justifies the derogation from the rule laid down in Article 21, in the event of recourse to Article 16, by reference to the first paragraph of Article 28 of the Brussels Convention, according to which decisions given in the State of the court first seised in disregard of the exclusive jurisdiction of the court second seised, based on Article 16 of the Convention, cannot be recognised in any Contracting State. It would therefore be inconsistent to require, under Article 21 of the Convention, that the second court, which alone has jurisdiction, should stay proceedings and decline jurisdiction in favour of a court which has no jurisdiction. Such a course of action would result in parties obtaining a decision from a court lacking jurisdiction, which could not take effect in the Contracting State where it was given. In such circumstances, the aim of the Brussels Convention, which is to improve legal protection and for that purpose to ensure the cross-border recognition and enforcement of judgments in civil matters would not be attained.
37
38
39
Referring to paragraph 23 of
40
Finally, the Commission and the Italian Government observe that the jurisdiction referred to in Article 17 of the Brussels Convention is distinguished from that referred to in Article 16 thereof in that, within the scope of the latter article, the parties cannot conclude agreements conferring jurisdiction contrary to Article 16 (Article 17(3)). Moreover, the parties are entitled at any time to cancel or amend a jurisdiction clause of the kind referred to in Article 17. Such a case would arise, for example, where, under Article 18 of the Convention, a party brought an action in a State other than that to the courts of which jurisdiction has been attributed and the other party enters an appearance before the court seised without contesting its jurisdiction (see to that effect Case 150/80
[1981] ECR 1671, paragraphs 10 and 11).
Findings of the Court
41
, cited above, paragraph 8). It follows that, in order to achieve those aims, Article 21 must be interpreted broadly so as to cover, in principle, all situations of
before courts in Contracting States, irrespective of the parties' domicile (
, cited above, paragraph 16).
42
From the clear terms of Article 21 it is apparent that, in a situation of
, the court second seised must stay proceedings of its own motion until the jurisdiction of the court first seised has been established and, where it is so established, must decline jurisdiction in favour of the latter.
43
In that regard, as the Court also observed in paragraph 13 of
44
It is true that, in paragraph 26 of
45
However, it is clear from paragraph 20 of the same judgment that, in the absence of any claim that the court second seised had exclusive jurisdiction in the main proceedings, the Court of Justice simply declined to prejudge the interpretation of Article 21 of the Convention in the hypothetical situation which it specifically excluded from its judgment.
46
In this case, it is claimed that the court second seised has jurisdiction under Article 17 of the Convention.
47
However, that fact is not such as to call in question the application of the procedural rule contained in Article 21 of the Convention, which is based clearly and solely on the chronological order in which the courts involved are seised.
48
, paragraph 23).
49
50
The fact nevertheless remains that, despite the reference to usage in international trade or commerce contained in Article 17 of the Brussels Convention, real consent by the parties is always one of the objectives of that provision, justified by the concern to protect the weaker contracting party by ensuring that jurisdiction clauses incorporated in a contract by one party alone do not go unnoticed (Case C-106/95
[1997] ECR I-911, paragraph 17 and
, paragraph 19).
51
[1992] ECR I-1745, paragraph 14).
52
Moreover, the interpretation of Article 21 of the Brussels Convention flowing from the foregoing considerations is confirmed by Article 19 of the Convention which requires a court of a Contracting State to declare of its own motion that it has no jurisdiction only where it is seised of a claim which is principally concerned with a matter over which the courts of another contracting State have exclusive jurisdiction by virtue of Article 16. Article 17 of the Brussels Convention is not affected by Article 19.
53
54
The third question
55
Admissibility
56
The Commission raises doubts as to the admissibility of this question and, therefore, of the questions which follow it and are related to it, on the ground that the national court has not provided concrete information such as to allow the inference that the Tribunale Civile e Penale di Roma has failed to fulfil its obligation to give judgment within a reasonable time and thereby infringed Article 6 of the European Convention for the safeguard of Human Rights and Fundamental Freedoms, signed in Rome on 4 November 1950 (hereinafter the ECHR).
57
58
It is therefore necessary to answer the third question.
Substance
Observations submitted to the Court
59
According to Gasser, Article 21 of the Brussels Convention must be interpreted in any event as excluding excessively protracted proceedings (that is to say of a duration exceeding three years), which are contrary to Article 6 of the ECHR and would entail restrictions on freedom of movement as guaranteed by Articles 28 EC, 39 EC, 48 EC and 49 EC. It is the responsibility of the European Union authorities or the national courts to identify those States in which it is well known that legal proceedings are excessively protracted.
60
61
62
The automatic application of Article 21 in such a case would grant the potential debtor a substantial and unfair advantage which would enable him to control the procedure, or indeed dissuade the creditor from enforcing his rights by legal proceedings.
63
In those circumstances, the United Kingdom Government suggests that the Court should recognise an exception to Article 21 whereby the court second seised would be entitled to examine the jurisdiction of the court first seised where
(2)
the court first seised has not decided the question of its jurisdiction within a reasonable time.
64
The United Kingdom Government adds that those conditions should be appraised by the national courts, in the light of all the relevant circumstances.
65
66
According to MISAT, the effect of an affirmative answer to the third question would be to create legal uncertainty and increase the financial burden for litigants, who would be required to pursue proceedings at the same time in two different States and to appear before the two courts seised, without being in a position to foresee which court would give judgment before the other. The already abundant litigation on the jurisdiction of courts would thereby be pointlessly increased, contributing to paralysis of the legal system.
67
The Commission states that the Brussels Convention is based on mutual trust and on the equivalence of the courts of the Contracting States and establishes a binding system of jurisdiction which all the courts within the purview of the Convention are required to observe. The Contracting States can therefore be obliged to ensure mutual recognition and enforcement of judgments by means of simple procedures. This compulsory system of jurisdiction is at the same time conducive to legal certainty since, by virtue of the rules of the Brussels Convention, the parties and the courts can properly and easily determine international jurisdiction. Within this system, Section 8 of Title II of the Convention is designed to prevent conflicts of jurisdiction and conflicting decisions.
68
only if they consider that the court first seised will give judgment within a reasonable period. Nowhere does the Convention provide that courts may use the pretext of delays in procedure in other contracting States to excuse themselves from applying its provisions.
69
Findings of the Court
70
71
First, the Convention contains no provision under which its articles, and in particular Article 21, cease to apply because of the length of proceedings before the courts of the Contracting State concerned.
72
73
The fourth, fifth and sixth questions
74
In view of the answer given to the third question, it is unnecessary to answer the fourth, fifth and sixth questions, which were submitted by the national court only in the event of the third question being answered in the affirmative.
Costs
75
The costs incurred by the Italian and United Kingdom Governments and by the Commission, which have submitted observations to the Court, are not recoverable. Since these proceedings are, for the parties to the main proceedings, a step in the action pending before the national court, the decision on costs is a matter for that court.
On those grounds,
THE COURT (Full Court),
in answer to the questions referred to it by the Oberlandesgericht Innsbruck by judgment of 25 March 2002, hereby rules:
1. A national court may, under the Protocol of 3 June 1971 on the interpretation by the Court of Justice of the Convention of 27 September 1968 on Jurisdiction and the Enforcement of Judgments in Civil and Commercial Matters, as amended by the Convention of 9 October 1978 on the accession of the Kingdom of Denmark, Ireland and the United Kingdom of Great Britain and Northern Ireland, by the Convention of 25 October 1982 on the accession of the Hellenic Republic, by the Convention of 26 May 1989 on the accession of the Kingdom of Spain and the Portuguese Republic and by the Convention of 29 November 1996 on the accession of the Republic of Austria, the Republic of Finland and the Kingdom of Sweden, refer to the Court of Justice a request for interpretation of the Brussels Convention, even where it relies on the submissions of a party to the main proceedings of which it has not yet examined the merits, provided that it considers, having regard to the particular circumstances of the case, that a preliminary ruling is necessary to enable it to give judgment and that the questions on which it seeks a ruling from the Court are relevant. It is nevertheless incumbent on the national court to provide the Court of Justice with factual and legal information enabling it to give a useful interpretation of the Convention and to explain why it considers that a reply to its questions is necessary to enable it to give judgment. 2. Article 21 of the Brussels Convention must be interpreted as meaning that a court second seised whose jurisdiction has been claimed under an agreement conferring jurisdiction must nevertheless stay proceedings until the court first seised has declared that it has no jurisdiction. 3. Article 21 of the Brussels Convention must be interpreted as meaning that it cannot be derogated from where, in general, the duration of proceedings before the courts of the Contracting State in which the court first seised is established is excessively long.
|
Skouris |
Jann |
Timmermans |
|
Gulmann |
Cunha Rodrigues |
Rosas |
|
Edward |
La Pergola |
Puissochet |
|
Schintgen |
Macken |
Colneric |
|
von Bahr |
Delivered in open court in Luxembourg on 9 December 2003.
|
R. Grass |
V. Skouris |
| Registrar | President |
–
Language of the case: German.
Source
-
EUR-Lex
EUR-Lex is a legal portal maintained by the Publications Office with the aim to enhance public access to European Union law.
Except where otherwise stated, all intellectual property rights on EUR-Lex data belong to the European Union.
© European Union, http://eur-lex.europa.eu/, 1998-2015 Link to document text: http://eur-lex.europa.eu/legal-content/EN/ALL/?uri=CELEX:62002CJ0116





